Town of Orangetown v. Magee Case Brief
LSD Deep Dive ∘ Audio Lesson
A two-host discussion of this case - listen on your commute or between classes
Case Brief Summary & Legal Analysis
tl;dr: Orangetown revoked a developer’s building permit solely for political reasons after substantial construction expenditures. The court affirmed reinstatement of the permit and a $5,137,126 damages award, holding that the arbitrary revocation violated substantive due process and was attributable to the Town.
Legal Significance: The decision distinguishes finality from exhaustion in land-use § 1983 claims. An arbitrary-conduct claim requires a final municipal decision but not pursuit of compensation procedures. It also recognizes municipal liability for a politically motivated permit revocation by an official vested with exclusive revocation authority.
Case Facts & Court Holding
Key Facts & Case Background
Bradley Industrial Park, Inc., owned by John and Patrick Magee, acquired 34 acres in Orangetown to construct an industrial building. The Town approved the plans and issued a building permit in 1980. Although the permit specified land clearing, footings, and foundations, the courts below determined that it authorized completion if subsequent plans conformed to the approved building plans. The trial court found that defendants spent over $4 million on land and building improvements before work stopped.
After organized community opposition intensified, the Town Supervisor directed the Building Inspector to revoke the permit, which he did on July 25, 1985. The Town later amended its zoning code to prohibit commercial construction on the property. The trial court found that the asserted grounds for revocation lacked evidentiary support and that revocation served solely political concerns.
The Town sued to compel removal of a temporary construction building. Defendants counterclaimed for permit reinstatement and damages under 42 USC § 1983. After a bifurcated trial, Supreme Court dismissed the complaint, ordered reinstatement, and awarded $5,137,126, costs, and attorney’s fees. The Appellate Division remitted the attorney’s-fee question and otherwise affirmed, then granted the Town leave to appeal.
Court Holding & Legal Precedent
Issue: Were defendants entitled to permit reinstatement and § 1983 damages when the Building Inspector, exercising exclusive statutory revocation authority at the Town Supervisor’s direction, revoked their vested building permit solely for political reasons without an appeal to the Zoning Board?
The court affirmed the Appellate Division’s order, with costs, and answered the certified question in the affirmative. Defendants’ substantial reliance on a legally issued permit established vested rights warranting reinstatement. The Building Inspector’s revocation was final, arbitrary, and attributable to the Town, supporting substantive due process damages under § 1983. The damages award stood because its calculation used figures supported by evidence or stipulation and a method the parties had accepted; the court expressly declined to endorse that method’s general appropriateness.
IRAC Legal Analysis
Legal Issue
Were defendants entitled to permit reinstatement and § 1983 damages when the Building Inspector, exercising exclusive statutory revocation authority at the Town Supervisor’s direction, revoked their vested building permit solely for political reasons without an appeal to the Zoning Board?
Conclusion
The decision supports § 1983 liability for arbitrary destruction of vested development rights through a final decision attributable to municipal policy. Its damages ruling rests on the parties’ agreement and does not generally approve the Wheeler formula.
Legal Rule
A landowner acquires vested development rights through substantial changes and expenditures in reliance on a valid permit when municipal interference would cause serious loss rendering the improvements essentially valueless (Matter of Putnam Armonk v Town of Southeast, 52 AD2d 10, 14-15; People v Miller, 304 NY 105, 109). A substantive due process claim challenging arbitrary land-use action requires a final decision, but not exhaustion of administrative review or pursuit of state compensation procedures (Williamson Planning Commn. v Hamilton Bank, 473 US 172, 192-194; Southview Assocs. v Bongartz, 980 F2d 84, 96-97; Patsy v Florida Bd. of Regents, 457 US 496). A protected property entitlement cannot be destroyed through municipal action lacking a legitimate reason (Board of Regents v Roth, 408 US 564, 577; Shelton v City of Coll. Sta., 780 F2d 475, 483). Municipal § 1983 liability may arise from a single act by an official authorized to decide municipal policy in the relevant area (Monell v New York City Dept. of Social Servs., 436 US 658, 690; Pembaur v Cincinnati, 475 US 469, 480, 482-483).
Legal Analysis
The affirmed factual findings established substantial commitment to the permitted development. Because the permit’s lawful issuance was undisputed and revocation rested on unlawful grounds, defendants were entitled to reinstatement under the zoning ordinances effective when revocation occurred.
The court analyzed the damages claim as a substantive due process challenge to an arbitrary decision, rather than deciding the asserted taking theories. Applying Williamson and Southview, it required finality but distinguished that requirement from exhaustion. Local law gave the Building Inspector exclusive authority to revoke permits; the Zoning Board could only review his completed decision. Requiring that appeal would therefore impose an impermissible exhaustion requirement.
Under Roth and the entitlement authorities, defendants possessed more than an expectation of continued construction: their rights had vested, and the courts below found they unquestionably would have obtained the remaining limited authorizations. Revocation lacked legal justification and served entirely political concerns, violating the protection against arbitrary or irrational destruction of that interest.
Under Monell and Pembaur, liability required municipal policy rather than respondeat superior. The Town’s code vested revocation authority solely in the Building Inspector, who exercised that authority at the Supervisor’s direction for political reasons. His action was therefore attributable to the Town.
The parties accepted the Wheeler damages formula and stipulated to several inputs. Applying the principle that civil litigants may chart their own course, the court upheld the calculation because it offended no public policy and rested on stipulated or evidentially supported figures. It expressly left the formula’s general suitability undecided.
The Opinion
Summary
- A developer acquires a vested property right under New York law by making substantial expenditures in reliance on a validly issued permit.
- An arbitrary and politically motivated revocation of such a permit violates substantive due process, giving rise to a 42 USC § 1983 claim for damages against the municipality.
- A § 1983 claim is ripe once an official with final policymaking authority acts; an appeal to a zoning board is not required.
Full text
Complete unedited opinion text as published by the court
\*46 OPINION OF THE COURT
This appeal involves a zoning dispute in which the courts below have found that plaintiff Town of Orangetown wrongfully revoked defendants’ permit to develop real property in the Town. Defendants have obtained injunctive relief restoring the building permit and an award of substantial damages on a 42 USC § 1983 cause of action. We now affirm.
I
Defendant Bradley Industrial Park, Inc. is the owner of 34 acres of land located in the Town of Orangetown. It acquired the property in 1979 to construct a 184,000 square foot industrial building at an estimated cost of $3 million. Defendants John and Patrick Magee are the shareholders of the corporation. In 1980 defendants’ plans for the improvement were approved and the Building Inspector issued a permit. Defendants began clearing and developing the site shortly thereafter. The trial court found that defendants spent over $4 million on the improvements for the land and building before work was halted by the Town. 1
Although the permit was limited to "land clearing, footings and foundations,” the courts below determined that the permit entitled defendants to construct the entire building as long as the subsequent plans for the walls, ceilings and electrical wiring comported with the plans for the building already approved by the Town’s Building Inspector.
As the work on the project progressed, organized resistance to it developed within the community. Ultimately, the opposition became so intense that the Town Supervisor directed the Building Inspector to revoke the defendants’ permit and on July 25, 1985 he did so. The Town subsequently amended its Zoning Code to preclude construction of commercial buildings \*47 on defendants’ land. 2 At trial, the Town offered a number of reasons for the revocation. The court concluded that most were not authorized by the Town’s ordinances and none were supported by the evidence. It found that the permit was revoked solely to satisfy political concerns.
Defendants had erected a temporary building for use during the preliminary stages of construction and after the permit was revoked, the Town instituted this action to obtain an order compelling its removal. Defendants counterclaimed seeking (1) an order compelling reinstatement of the permit, and (2) damages pursuant to 42 USC § 1983. After a bifurcated trial, Supreme Court dismissed the complaint and entered a judgment in favor of defendants on their counterclaims ordering reinstatement of the building permit and awarding damages of $5,137,126, costs and attorney’s fees. The Appellate Division modified the judgment by remitting the question of attorney’s fees and otherwise affirmed. It subsequently granted the Town leave to appeal to this Court. Our review is controlled in large part by factual findings of the trial court, affirmed by the Appellate Division.
II
The CPLR Article 78 Claim
In their first counterclaim defendants sought reinstatement of their building permit, alleging they had a "vested right” in the planned construction.
In New York, a vested right can be acquired when, pursuant to a legally issued permit, the landowner demonstrates a commitment to the purpose for which the permit was granted by effecting substantial changes and incurring substantial expenses to further the development (see, Matter of Putnam Armonk v Town of Southeast, 52 AD2d 10, 14-15; see also, People ex rel. Ortenberg v Bales, 250 NY 598, affg 224 App Div 87; City of Buffalo v Chadeayne, 134 NY 163, 165; Matter of Caponi v Walsh, 228 App Div 86, 89). Neither the issuance of a permit (see, Matter of Sibarco Stas. v Town Bd., 24 NY2d 900; Rice v Van Vranken, 132 Misc 82, affd 225 App Div 179, affd 255 NY 541; People ex rel. Ortenberg v Bales, supra) nor the landowner’s substantial improvements and expenditures, standing alone, will establish the right. The landowner’s actions relying on a \*48 valid permit must be so substantial that the municipal action results in serious loss rendering the improvements essentially valueless (see, People v Miller, 304 NY 105, 109).
There is no dispute that defendants’ permit was legally issued. Whether defendants had sufficiently committed the land to the use authorized by the permit prior to revocation is a question of fact and the determination of the courts below that they had is supported by evidence in the record (see, Matter of Caponi v Walsh, supra; see generally, 1 Anderson, New York Zoning Law and Practice § 6.18, at 231 [3d ed]). Inasmuch as the permit was revoked for unlawful reasons, the revocation resulted in an unconstitutional deprivation of defendants’ property rights (see, People v Miller, supra). Accordingly, defendants are entitled to reinstatement of the building permit in conformity with the zoning ordinances in effect at the time of the revocation.
ra
The Civil Rights Claim
Defendants’ second counterclaim asserted a cause of action under 42 USC § 1983 for damages suffered as a result of the Town’s actions. Defendants claimed that plaintiff’s actions resulted in an unconstitutional taking of their property and that the Town denied them substantive and procedural due process guaranteed by the United States Constitution.
Section 1983 provides:
"Every person who, under color of any statute, ordinance, regulation, custom or usage, of any State * * * , subjects, or causes to be subjected, any citizen of the United States or other person within the jurisdiction thereof to the deprivation of any rights, privileges, or immunities secured by the Constitution and laws, shall be liable to the party injured in an action at law, suit in equity, or other proper proceeding for redress”.
Municipalities are "persons” subject to suit under section 1983 for the deprivation of constitutionally protected rights caused by actions which "implement! ] or execute! ] a policy statement, ordinance, regulation, or decision officially adopted and promulgated by [its] officers” (Monell v New York City Dept. of Social Servs., 436 US 658, 690; Pembaur v Cincinnati, 475 US 469, 479-480). The municipality may not be held vicari \*49 ously liable under the doctrine of respondeat superior for employing a careless tortfeasor, however: the injury must arise from acts of municipal officers or employees in the course of executing municipal policy or custom (id). Liability may even be imposed for a single act, as long as it is the act of an official authorized to decide policy in that area (Pembaur, supra, at 480, 482-483; St. Louis v Praprotnik, 485 US 112, 123-124; see also, Comer, Municipal Liability Under Section 1983: The Rationale Underlying the Final Authority Doctrine, 44 Vand L Rev 341 [1991]).
In the context of land use, section 1983 provides protection against municipal actions which violate a landowner’s rights under the Just Compensation Clause of the Fifth Amendment or the Due Process Clauses of the Fifth and Fourteenth Amendments to the United States Constitution. Under the former, the claimant must establish that the governmental action amounts to a taking without just compensation. The Supreme Court has also identified, although not yet recognized, a substantive due process claim under the Fifth and Fourteenth Amendments based upon a regulatory taking, i.e., regulation of property that goes so far it has effectively destroyed the economic value of the property (see, Williamson Planning Commn. v Hamilton Bank, 473 US 172, 185, 197-200).
The trial court rested its decision on a third ground — that the acts of the Town in revoking defendants’ permit denied them substantive due process of law because the revocation and subsequent zoning change were arbitrary and capricious (156 Misc 2d 881, 893-895, supra; and see, Southview Assocs. v Bongartz, 980 F2d 84, 96, 102 [2d Cir 1992], cert denied sub nom. Southview Assocs. v Individual Members of Vt. Envtl. Bd., 507 US 987 [1993]; Brady v Town of Colchester, 863 F2d 205, 215 [2d Cir 1988]; Wheeler v City of Pleasant Grove, 664 F2d 99 [5th Cir 1981]; see generally, Stein, Regulatory Takings and Ripeness in the Federal Courts, 48 Vand L Rev 1, 80 [1995]). 3 This type of claim challenges a particular land-use decision — here, the revocation of plaintiff’s building permit — as a single decision with its own consequences, rather than as one in a series of action — resulting in a taking (see, Harris v County of Riverside, 904 F2d 497, 501, supra). The key factor in such cases is not whether the State was justified in depriving the in \*50 dividual of his or her property, but rather whether the State obeyed the strictures of the Constitution in doing so (see, Weissman v Fruchtman, 700 F Supp 746, 756 [SD NY]).
A
Plaintiff’s Ripeness Defense
In contesting the trial court’s determination, the Town first contends that the revocation was not "final” and therefore not ripe for judicial review, until reviewed by the Orangetown Zoning Board of Appeals. Defendants, on the other hand, assert that the Building Inspector constitutes a Town official with final policy-making authority and that requiring an appeal to the Town Zoning Board of Appeals would impose an impermissible exhaustion of remedies requirement on their section 1983 claim.
Civil rights claims are not justiciable until the municipality has "arrived at a definitive position on the issue that inflicts an actual, concrete injury” (Williamson, supra, at 193; Matter of Ward v Bennett, 79 NY2d 394, 400). This requirement reflects the reluctance of the courts to impose liability upon a municipality unless the liability arises from "acts which the municipality has officially sanctioned or ordered” (Pembaur, supra, at 480; Monell, supra, at 691; de St. Aubin v Flacke, 68 NY2d 66, 75).
The ripeness requirements for just compensation and regulatory "takings” claims differ from claims based upon arbitrary and capricious conduct. Under takings claims the contention is that the State has taken the property for a governmental purpose or that it has gone "too far” in exercising its police power to regulate property and thus deprived an owner of all economically beneficial use of the property (Pennsylvania Coal Co. v Mahon, 260 US 393, 415; see, Northern Westchester Professional Park Assocs. v Town of Bedford, 60 NY2d 492; French Investing Co. v City of New York, 39 NY2d 587, cert denied 429 US 990). Such claims are not ripe for judicial review until (1) the governmental entity charged with implementing the regulations has rendered a final decision regarding the application of the regulations to the property, and (2) the landowner has availed itself of the procedures provided by State law to obtain just compensation (Williamson, supra, at 194, 200; Southview, supra, at 96). Under this type of claim, a decision does not become ripe for review unless alternative uses of the property have been considered and rejected and it is thus \*51 established that the landowner has been deprived of its property. Until that has been done, it is not clear that a taking has occurred or how "far” the regulation goes.
However, a substantive due process claim based on arbitrary and capricious conduct is subject only to the final decision requirement of the Williamson test. The decision must be final to be reviewable (else how could arbitrariness be judged), but it is unnecessary that the landowner pursue administrative remedies to determine how the regulation in question applies to the property or avail itself of State procedures for determining compensation (see, Southview Assocs. v Bongartz, supra, at 96-97). If the action of the municipality is arbitrary and capricious, the remedy for a violation is invalidation of the regulation and actual damages (see, Williamson, supra, at 197).
There should be no confusion about the requirement that administrative remedies must be exhausted in some cases before judicial review is available and the requirement that an action must be final before it is ripe for judicial review. The finality requirement is concerned with whether an official authorized to make the determination has arrived at a decision that inflicts injury. The requirement that administrative review must be exhausted in some cases relates to the procedure by which a party injured by a decision may seek review and obtain a remedy if the decision is found to be unlawful (Williamson, supra, at 192-193; see also, Church of St. Paul & St. Andrew v Barwick, 67 NY2d 510, 521). If the Building Inspector had the authority to make a final decision revoking defendants’ permit, requiring defendants to seek administrative review of his action by taking an appeal to the Zoning Board would impose an exhaustion requirement on their section 1983 action, a condition which is generally impermissible (see, Patsy v Florida Bd. of Regents, 457 US 496; Williamson, supra, at 194, n 13; see generally, Stein, Regulatory Takings and Ripeness in the Federal Courts, op. cit, at 15; 1 Schwartz and Kirklin, Section 1983 Litigation: Claims, Defenses, and Fees § 3.13, at 204-205 [2d ed]).
"Whether the Building Inspector’s revocation constituted a "final decision” of the Town of Orangetown is a matter to be determined by examining the relevant local laws. States have broad discretion to determine the form of local government and the distribution of power in one locality may be quite different from that of another. Whether- an official has final authority to take municipal action in a given case is not a question of fact, but a question of State law (St. Louis v Prapro \*52 tnik, supra, at 124; Pembaur, supra, at 483; see generally, Stein, op. cit., at 82).
Under the ordinances of the Town of Orangetown, the Building Inspector had the statutory authority to effect a revocation of defendants’ building permit (Orangetown, N. Y., Zoning Code, ch 43, § 8.222 [1969]). He was the "initial decision-maker” vested by law with the exclusive and unfettered authority to decide the question of revocation (see, Williamson, supra, at 193) and he clearly had done so when he revoked defendants’ permit and halted work on the project. The Zoning Board was not authorized to revoke a permit or even participate in the Inspector’s decision to revoke. Its power was restricted to the review of the Inspector’s final decision. Thus, a determination by the Board was not necessary and defendants’ counterclaim for section 1983 relief is ripe for judicial review.
B
Defendants’ Section 1983 Claim
To succeed on their claim for damages pursuant to 42 USC § 1983, defendants must establish (1) the deprivation of a protectable property interest (2) by one acting under the authority of law (Parratt v Taylor, 451 US 527, 535).
The hallmark of property "is an individual entitlement grounded in state law, which cannot be removed except 'for cause’ ” (Logan v Zimmerman Brush Co., 455 US 422, 430; Parratt v Taylor, supra; Matter of Deas v Levitt, 73 NY2d 525, 531, cert denied 493 US 933). In order to establish a protectable property interest in the building permit, defendants must show more than a mere expectation or hope to retain the permit and continue their improvements; they must show that pursuant to State or local law, they had a "legitimate claim of entitlement” to continue construction (Board of Regents v Roth, 408 US 564, 577; Sullivan v Town of Salem, 805 F2d 81, 84-85 [2d Cir 1986]; Yale Auto Parts v Johnson, 758 F2d 54, 59 [2d Cir 1985]).
Defendants did so in this case by establishing that the rights to develop their land had become vested under State law. Moreover, as the courts below found, they unquestionably would have received the limited future authorizations necessary to complete the project. On this evidence, the Town had "engendered a clear expectation of continued enjoyment” of the permit sufficient to constitute a protectable property inter \*53 est for purposes of a section 1983 claim (Barry v Barchi, 443 US 55, 64, n 11); there was a "certainty or a very strong likelihood” that defendants would have completed the project absent the deprivation of due process (see, Yale Auto Parts, supra, at 59).
Having acquired a cognizable property interest, due process assures the defendants the right to be free from arbitrary or irrational municipal actions destructive of this interest (see, Arlington Hgts. v Metropolitan Hous. Corp., 429 US 252, 267; Southview Assocs., supra, at 96; Brady v Town of Colchester, supra, at 215). The municipality’s authority to regulate zoning rests upon the valid exercise of its police power and a decision regulating a landowner’s use of its property offends due process when the government acts with "no legitimate reason for its decision” (Shelton v City of Coll. Sta., 780 F2d 475, 483 [5th Cir], cert denied 479 US 822; see, Euclid v Ambler Co., 272 US 365, 395). The evidence in the record supports the trial court’s conclusion that the Building Inspector’s revocation of defendants’ permit was arbitrary and capricious in this case because it was without legal justification and motivated entirely by political concerns. The only remaining question is whether his actions may be imputed to the Town of Orangetown.
The Town Zoning Code, which necessarily reflects Town policy, vests the Building Inspector, alone, with the authority to revoke building permits (Town of Orangetown Code, ch 43, § 8.222). The Building Inspector therefore implements Town policy and the Town, by enacting the legislation, accepted the possibility that he would exercise this authority in an arbitrary and capricious manner. While the municipality might not be liable if the Building Inspector acted in a good faith or mistaken understanding of the law (see, Brady v Town of Colchester, supra, at 216) or if his act was a random act of personal ill will not authorized by the Town (see, Monell, supra; Pembaur, supra), that clearly was not the case here. He exercised his legal authority for political reasons at the direction of the Town Supervisor.
Accordingly, defendants successfully established a claim for damages pursuant to 42 USC § 1983, based on the Building Inspector’s arbitrary and irrational revocation of their building permit.
\*54 IV
Damages
Finally, the plaintiff maintains that the damages were incorrectly computed and the award excessive.
Plaintiffs experts conceded during trial that defendants had sustained substantial damages. Moreover, they agreed that the damages could be measured by implementing the so-called Wheeler formula (see, Wheeler v City of Pleasant Grove, 833 F2d 267, 271 [11th Cir 1987] [Wheeler III]; see also, 664 F2d 99 [Wheeler I], supra; 746 F2d 1437 [Wheeler II]; 896 F2d 1347, 1351 [Wheeler IV]). In fact, the parties stipulated to a number of figures that could be used to compute the damages under that formula.
In Wheeler, a case remarkably similar to this on the facts, the court established a method for determining the damages sustained by temporary governmental interference with a landowner’s beneficial use of property. It held that the loss takes the form of an injury to the property’s potential for producing income or an expected profit. The compensable interest is the return on the portion of fair market value that is lost as a result of the government’s action. Accordingly, the landowner should be awarded the market rate of return computed over the period of the taking on the difference between the property’s fair value without the restriction and its fair market value with the restriction (see, 833 F2d 267, 271, supra).
The parties to a civil dispute are free to chart their own course and, unless public policy is affronted, they may fashion the way a controversy is to be resolved or how damages are to be computed without interference by the courts (Mitchell v New York Hosp., 61 NY2d 208; Matter of Abramovich v Board of Educ., 46 NY2d 450, cert denied 444 US 845). While we express no view on the appropriateness of the Wheeler formula to measure damages in cases such as this, its use does not affront public policy and it was within the court’s discretion to compute the damages on the basis of the formula as the parties agreed it should.
Implementing that formula, the Town stipulated to values for the building and the land before and after taking, the difference between the two numbers, the equity ratio and the market rate of return. The court determined other values based upon the evidence and directed the parties to compute the damages using the Wheeler formula and submit their determination. It based its final award on those submissions. Inasmuch \*55 as the figures used were either supported by evidence or agreed upon by the parties, there is no basis to interfere with the award.
Accordingly, the order of the Appellate Division should be affirmed, with costs, and the certified question answered in the affirmative.
Chief Judge Kaye and Judges Titone, Bellacosa, Smith, Levine and Ciparick concur.
Order affirmed, etc.
. In addition to the estimated cost of site and building improvements, the trial court found that defendants spent $250,000 on the purchase of the original site, approximately $123,000 purchasing additional acreage to satisfy Town requirements for access to public roads; that in response to community complaints about highway congestion, defendants spent approximately $250,000 developing an alternate route over a railroad crossing; defendants spent $100,000 for water and sewage lines; and in certain easement negotiations with the water company, defendant gave up rights in a self-contained water system on the property worth approximately $1 million.
. The facts are set out fully in the decision of Justice Stolarik reported at 156 Misc 2d 881.
. Some Federal courts analyze such claims as matters of procedural due process (see, Nasierowski Bros. Inv. Co. v City of Sterling Hgts., 949 F2d 890, 894 [6th Cir 1991]; Harris v County of Riverside, 904 F2d 497 [9th Cir 1990]; Landmark Land Co. v Buchanan, 874 F2d 717, 723 [10th Cir 1989]).